Apply for building permission through ODPS (Online Development Permission System)
The process is digitized through the ODPS and follows these 6 key steps
Architect/Engineer/Developer must register as a "Person on Record" (POR) and the Citizen must create an account on the e-Nagar portal.
The architect prepares the building plan using Pre-DCR software to ensure it complies with GDCR (General Development Control Regulations).
The applicant logs in, selects "Building Permission," fills in the property details (TP/FP/Survey No.), and uploads the Pre-DCR drawing file.
Upload all required land and identity documents. The system performs an automated technical scrutiny of the drawings.
Once the plan is technically verified, the system calculates the scrutiny and development fees. These must be paid online via the "Quick Pay" or dashboard link.
After field verification by a municipal inspector (if required), the competent authority approves the plan, and a digitally signed Building Permission certificate is generated for download.
While requirements may vary slightly based on the project type (Residential vs. Commercial), the following are standard:
| Service Type | Est. Duration |
|---|---|
| License Registration | 30 Days |
| Building Registration | 7 to 15 Days |
| Building Use (BU) Permission | 8 to 21 Days after final inspection. |